📘 Section 31: Creating an Assumptions Log

By Daniel Nguyen
Published in PMP
April 06, 2025
5 min read
📘 Section 31: Creating an Assumptions Log

Creating an Assumptions Log

An Assumptions Log is a vital document in project management, used to capture assumptions and constraints throughout the project lifecycle. It is initially developed during project initiation and updated as the project progresses.


1. What is an Assumptions Log?

An Assumptions Log records:

  • Assumptions: Factors considered true or certain for planning purposes, without definitive proof.
  • Constraints: Restrictions or limitations that impact the project’s execution, such as budget, schedule, or resources.

2. Importance of an Assumptions Log

  1. Clarity: Ensures everyone understands the basis of decisions.
  2. Risk Management: Helps identify risks if assumptions prove false.
  3. Accountability: Documents rationale for project planning and execution.
  4. Traceability: Provides a historical record of assumptions and constraints.

3. Key Components of an Assumptions Log

FieldDescription
IDUnique identifier for each assumption or constraint.
DescriptionDetailed description of the assumption or constraint.
CategoryClassify as assumption or constraint (e.g., technical, resource, financial).
OwnerPerson or team responsible for validating or addressing the item.
Date LoggedWhen the assumption or constraint was identified.
StatusOpen, validated, invalidated, or closed.
ImpactPotential effect on the project if the assumption proves false.
Resolution PlanSteps to confirm or address the assumption or constraint.

4. Steps to Create an Assumptions Log

  1. Identify Assumptions and Constraints

    • Gather input from stakeholders, project team members, and documentation.
    • Example Assumptions:
      • The required technology will be available.
      • Key personnel will be available during critical phases.
    • Example Constraints:
      • Budget is capped at $500,000.
      • The project must be completed within 6 months.
  2. Document Details

    • Record information in the log, including descriptions, owners, and status.
  3. Evaluate and Validate

    • Assess the impact and likelihood of each assumption being true.
    • Review constraints for realism and feasibility.
  4. Monitor and Update Regularly

    • Validate assumptions as the project progresses.
    • Address invalidated assumptions to mitigate risks.
    • Adjust project plans based on new information.

Example of an Assumptions Log

IDDescriptionCategoryOwnerDate LoggedStatusImpactResolution Plan
A001Client will approve deliverables in 5 daysAssumptionProject Lead2025-01-20OpenDelays in approvals could affect timelineConfirm with client during kick-off meeting
C001Budget is fixed at $100,000ConstraintSponsor2025-01-20ValidatedLimits scope; cannot add featuresPrioritize requirements based on budget

5. Common Challenges and Tips

  • Challenge: Overlooking critical assumptions during initiation.
    Tip: Facilitate workshops with stakeholders to uncover hidden assumptions.

  • Challenge: Not updating the log as the project evolves.
    Tip: Include log reviews in regular project meetings.

  • Challenge: Ambiguity in descriptions.
    Tip: Use clear and concise language to describe assumptions and constraints.


Sample Questions

1. Why is an Assumptions Log Important?

Options:
A. To track only the project’s financial constraints.
B. To ensure project planning is based on validated factors.
C. To replace the risk management plan.
D. To document changes to project deliverables.

Correct Answer:
B. To ensure project planning is based on validated factors.

2. How Often Should the Assumptions Log Be Updated?

Options:
A. Only during the initiation phase.
B. After every milestone or significant event.
C. Once, at the project close.
D. Monthly, regardless of project progress.

Correct Answer:
B. After every milestone or significant event.

3. What Should You Do When an Assumption is Invalidated?

Options:
A. Ignore it and continue with the project.
B. Update the log and assess its impact on the project.
C. Remove it from the log without further action.
D. Create a new assumption to replace it.

Correct Answer:
B. Update the log and assess its impact on the project.


Here’s a scenario-based question related to creating and managing an Assumptions Log:


Scenario 1: Managing Assumptions in a Complex Project

You are managing a software development project for a client with a strict deadline. During the project initiation phase, the following assumptions were logged:

  1. Assumption A: The development team will have full-time availability.
  2. Assumption B: All required software licenses will be procured by the client before development starts.
  3. Assumption C: Stakeholders will provide feedback on deliverables within 3 business days.

Midway through the project, you discover:

  • Two team members are now only available part-time due to reassignments.
  • The client delayed the procurement of software licenses, impacting the schedule.

Question:
What actions should you take to manage these invalidated assumptions, and what should be the immediate update to the Assumptions Log?


Options:

A. Ignore the changes, as these assumptions were only guidelines, and proceed with the project as planned.

B. Update the Assumptions Log to reflect the invalidation, escalate the issues to stakeholders, and assess the impact on the project timeline and deliverables.

C. Replace the invalidated assumptions with new ones and continue the project without updating the stakeholders.

D. Delay the project until all assumptions are revalidated and ignore the impact on the schedule.


Correct Answer:
B. Update the Assumptions Log to reflect the invalidation, escalate the issues to stakeholders, and assess the impact on the project timeline and deliverables.


Scenario 2: Addressing New Assumptions

You are managing a construction project for a new office building. The initial project assumptions include:

  1. The weather will remain favorable for outdoor construction activities.
  2. Required permits will be approved within 30 days of submission.

Midway through the project:

  • Unforeseen bad weather causes delays in completing the foundation.
  • One of the required permits is delayed due to administrative backlog.

Question:
What actions should you take to address these changes?

Options:
A. Update the Assumptions Log with details of the delays, adjust the project schedule, and communicate the impact to stakeholders.
B. Ignore the weather delays and focus on completing other project activities to stay on track.
C. Continue to wait for the permit and keep stakeholders informed only if further delays occur.
D. Remove the weather assumption from the log and proceed without documenting its impact.

Correct Answer:
A. Update the Assumptions Log with details of the delays, adjust the project schedule, and communicate the impact to stakeholders.


Scenario 3: Validating Assumptions During Execution

In a software implementation project, your assumptions include:

  1. The client will provide accurate data for migration.
  2. The IT team will be available for daily review meetings.

During execution, you discover:

  • The data provided by the client has several inconsistencies, requiring additional effort to clean and validate.
  • The IT team is only available twice a week due to other priorities.

Question:
How should you proceed to ensure the project remains on track?

Options:
A. Inform stakeholders of the risks caused by invalid assumptions, revise the project timeline, and update the Assumptions Log.
B. Continue with the project and attempt to clean the data without informing the client of the additional effort required.
C. Remove the invalid assumptions from the log without updating the timeline or stakeholders.
D. Ask the IT team to reallocate their resources and continue with the original assumptions.

Correct Answer:
A. Inform stakeholders of the risks caused by invalid assumptions, revise the project timeline, and update the Assumptions Log.


Scenario 4: Prioritizing Assumptions

Your project involves launching a new e-commerce website, and the following assumptions are documented:

  1. The web hosting provider will ensure 99.9% uptime.
  2. Marketing materials will be approved by the client within 2 days.
  3. The payment gateway integration will require no additional testing.

During testing, you notice:

  • The payment gateway integration is producing errors, requiring significant rework.
  • Marketing materials are delayed by 5 days.

Question:
Which assumption should you prioritize for immediate action, and why?

Options:
A. Marketing materials delay, as it directly impacts the go-live date.
B. Payment gateway errors, as they pose a risk to the website’s functionality.
C. Web hosting provider’s uptime, as it ensures customer access.
D. Both marketing and payment issues should be ignored until closer to the deadline.

Correct Answer:
B. Payment gateway errors, as they pose a risk to the website’s functionality.


Scenario 5: Managing Stakeholder Expectations

You are managing an event planning project. Assumptions include:

  1. The venue will accommodate 500 attendees comfortably.
  2. Vendors will deliver supplies 3 days before the event.

A week before the event, the venue informs you that capacity is reduced to 400 due to maintenance, and a key vendor delays delivery to the day before the event.

Question:
How should you manage stakeholder expectations in this situation?

Options:
A. Update the Assumptions Log, inform stakeholders of the capacity reduction, and negotiate earlier delivery with the vendor.
B. Proceed with 500 attendees as planned and hope the capacity issue resolves itself.
C. Remove the venue assumption from the log and focus on vendor delays.
D. Cancel the event and notify stakeholders after the original event date.

Correct Answer:
A. Update the Assumptions Log, inform stakeholders of the capacity reduction, and negotiate earlier delivery with the vendor.


Scenario 6: Proactively Identifying Risks from Assumptions

You are managing a research project, and one of the key assumptions is that survey responses will be collected within 4 weeks.

  • Two weeks into the project, you find that the response rate is only 30% of what was expected.
  • Your team suggests extending the survey window by 2 weeks.

Question:
What steps should you take to address this issue?

Options:
A. Update the Assumptions Log, communicate the risk to stakeholders, and adjust the project timeline to reflect the extension.
B. Ignore the low response rate and move forward with the available data.
C. Increase the survey sample size without consulting stakeholders.
D. Stop the project until the original assumption is validated.

Correct Answer:
A. Update the Assumptions Log, communicate the risk to stakeholders, and adjust the project timeline to reflect the extension.



Tags

#PMP

Share

Previous Article
🔍 JavaScript Destructuring

Table Of Contents

1
Creating an Assumptions Log
2
1. What is an Assumptions Log?
3
2. Importance of an Assumptions Log
4
3. Key Components of an Assumptions Log
5
4. Steps to Create an Assumptions Log
6
Example of an Assumptions Log
7
5. Common Challenges and Tips
8
Sample Questions