This process is critical in the Planning Process Group and ensures that all aspects of the project are integrated into a single, cohesive plan. The Project Management Plan serves as the primary document guiding project execution, monitoring, control, and closure.
Which of the following is NOT part of a typical Project Management Plan?
A. Scope Management Plan
B. Performance Baseline
C. Market Research Analysis
D. Schedule Management Plan
Correct Answer:
C. Market Research Analysis
What is the primary purpose of the Project Management Plan?
A. To document all risks associated with the project.
B. To outline how the project will be executed, monitored, controlled, and closed.
C. To replace the need for stakeholder communication.
D. To track employee productivity during the project.
Correct Answer:
B. To outline how the project will be executed, monitored, controlled, and closed.
You are finalizing the Project Management Plan for a construction project, but you notice the Risk Management Plan is incomplete.
What should you do next?
A. Finalize the Project Management Plan without the Risk Management Plan.
B. Develop the Risk Management Plan and integrate it before finalizing.
C. Proceed with execution and address risks as they arise.
D. Remove risk-related activities from the scope of the project.
Correct Answer:
B. Develop the Risk Management Plan and integrate it before finalizing.
A key stakeholder requests a significant change to the project scope after the Project Management Plan has been approved.
What is the correct process to address this request?
A. Implement the change immediately to maintain stakeholder satisfaction.
B. Update the Project Management Plan informally and inform the team.
C. Follow the Perform Integrated Change Control Process to assess and incorporate the change if approved.
D. Ignore the request, as the Project Management Plan is already approved.
Correct Answer:
C. Follow the Perform Integrated Change Control Process to assess and incorporate the change if approved.
Who is primarily responsible for the development of the Project Management Plan?
A. Project Sponsor
B. Project Team
C. Project Manager
D. Senior Management
Correct Answer:
C. Project Manager
Which process is used to update the Project Management Plan when changes are required?
A. Direct and Manage Project Work
B. Perform Integrated Change Control
C. Monitor Communications
D. Validate Scope
Correct Answer:
B. Perform Integrated Change Control
Scenario: During the development of the project management plan, a key stakeholder requests additional deliverables not included in the project charter.
Question:
What should the project manager do?
a. Include the additional deliverables in the plan.
b. Update the project charter to include the new deliverables.
c. Assess the impact of the change and submit a change request.
d. Reject the request as it is outside the charterโs scope.
Correct Answer: c. All changes must be evaluated and approved through the change control process.
Scenario: While integrating the plans, the project manager notices that the risk management plan conflicts with the schedule management plan.
Question:
What should the project manager do?
a. Finalize the schedule management plan and proceed.
b. Resolve the conflict by consulting relevant stakeholders.
c. Remove the conflicting sections from both plans.
d. Continue with the integration and address the conflict later.
Correct Answer: b. Conflicts between plans should be resolved to ensure consistency and alignment.
Quick Links
Legal Stuff
Social Media