HomeAbout Me

๐Ÿ“˜ Section 32: Developing the Project Management Plan

By Daniel Nguyen
Published in PMP
April 08, 2025
3 min read
๐Ÿ“˜ Section 32: Developing the Project Management Plan

This process is critical in the Planning Process Group and ensures that all aspects of the project are integrated into a single, cohesive plan. The Project Management Plan serves as the primary document guiding project execution, monitoring, control, and closure.


Key Characteristics

  • Purpose: Establishes a framework for managing the project and achieving objectives.
  • Iterative Process: Updated as new information becomes available or changes are approved.
  • Baseline-Driven: Contains baselines for scope, schedule, and cost for performance tracking.

Inputs

  1. Project Charter: High-level objectives, scope, and stakeholder expectations.
  2. Outputs from Other Processes: Plans and documents from subsidiary processes (e.g., Risk Management Plan, Schedule Management Plan).
  3. Enterprise Environmental Factors (EEFs): Organizational culture, industry standards, regulations.
  4. Organizational Process Assets (OPAs): Templates, guidelines, historical project information.

Tools and Techniques

  1. Expert Judgment: Leveraging expertise from stakeholders, team members, and industry experts.
  2. Data Gathering: Brainstorming, interviews, and focus groups to gather insights.
  3. Interpersonal and Team Skills: Facilitation and negotiation to align stakeholders.
  4. Meetings: Collaborative discussions to define and finalize the plan.

Outputs

  1. Project Management Plan:
    • Subsidiary Plans: Scope, schedule, cost, quality, resource, communication, risk, procurement, and stakeholder management plans.
    • Baselines: Scope baseline, schedule baseline, cost baseline.

Steps in Developing the Project Management Plan

  1. Understand the Project Charter: Align the plan with the objectives, constraints, and assumptions in the charter.
  2. Define Subsidiary Plans: Develop plans for managing specific areas (e.g., risk, resources).
  3. Set Baselines: Establish the scope, schedule, and cost baselines for performance measurement.
  4. Integrate Plans: Ensure all subsidiary plans align and work cohesively.
  5. Seek Stakeholder Input: Involve stakeholders to ensure buy-in and alignment.
  6. Obtain Approval: Finalize the plan and secure formal approval from the sponsor and key stakeholders.

Example Components of a Project Management Plan

1. Executive Summary

  • High-level overview of project objectives and key milestones.

2. Baselines

  • Scope Baseline: Work Breakdown Structure (WBS), scope statement, WBS dictionary.
  • Schedule Baseline: Approved timeline for deliverables.
  • Cost Baseline: Budget allocation for the project.

3. Subsidiary Plans

  • Scope Management Plan
  • Schedule Management Plan
  • Cost Management Plan
  • Risk Management Plan

4. Change Management Plan

  • Process for managing and controlling project changes.

5. Communication Management Plan

  • Stakeholder communication methods, frequency, and channels.

Questions

Question 1: Core Components

Which of the following is NOT part of a typical Project Management Plan?
A. Scope Management Plan
B. Performance Baseline
C. Market Research Analysis
D. Schedule Management Plan

Correct Answer:
C. Market Research Analysis


Question 2: Key Purpose

What is the primary purpose of the Project Management Plan?
A. To document all risks associated with the project.
B. To outline how the project will be executed, monitored, controlled, and closed.
C. To replace the need for stakeholder communication.
D. To track employee productivity during the project.

Correct Answer:
B. To outline how the project will be executed, monitored, controlled, and closed.


Question 3: Missing Subsidiary Plans

You are finalizing the Project Management Plan for a construction project, but you notice the Risk Management Plan is incomplete.

What should you do next?
A. Finalize the Project Management Plan without the Risk Management Plan.
B. Develop the Risk Management Plan and integrate it before finalizing.
C. Proceed with execution and address risks as they arise.
D. Remove risk-related activities from the scope of the project.

Correct Answer:
B. Develop the Risk Management Plan and integrate it before finalizing.


Question 4: Stakeholder Concerns

A key stakeholder requests a significant change to the project scope after the Project Management Plan has been approved.

What is the correct process to address this request?
A. Implement the change immediately to maintain stakeholder satisfaction.
B. Update the Project Management Plan informally and inform the team.
C. Follow the Perform Integrated Change Control Process to assess and incorporate the change if approved.
D. Ignore the request, as the Project Management Plan is already approved.

Correct Answer:
C. Follow the Perform Integrated Change Control Process to assess and incorporate the change if approved.


Question 5: Ownership

Who is primarily responsible for the development of the Project Management Plan?
A. Project Sponsor
B. Project Team
C. Project Manager
D. Senior Management

Correct Answer:
C. Project Manager


Question 6: Updates

Which process is used to update the Project Management Plan when changes are required?
A. Direct and Manage Project Work
B. Perform Integrated Change Control
C. Monitor Communications
D. Validate Scope

Correct Answer:
B. Perform Integrated Change Control


Question 7: Stakeholder Concerns

Scenario: During the development of the project management plan, a key stakeholder requests additional deliverables not included in the project charter.
Question:
What should the project manager do?
a. Include the additional deliverables in the plan.
b. Update the project charter to include the new deliverables.
c. Assess the impact of the change and submit a change request.
d. Reject the request as it is outside the charterโ€™s scope.
Correct Answer: c. All changes must be evaluated and approved through the change control process.


Question 8: Inconsistent Subsidiary Plans

Scenario: While integrating the plans, the project manager notices that the risk management plan conflicts with the schedule management plan.
Question:
What should the project manager do?
a. Finalize the schedule management plan and proceed.
b. Resolve the conflict by consulting relevant stakeholders.
c. Remove the conflicting sections from both plans.
d. Continue with the integration and address the conflict later.
Correct Answer: b. Conflicts between plans should be resolved to ensure consistency and alignment.


Tags

#PMP

Share

Previous Article
๐Ÿ“š JavaScript Arrays: The Essential Guide

Table Of Contents

1
Key Characteristics
2
Inputs
3
Tools and Techniques
4
Outputs
5
Steps in Developing the Project Management Plan
6
Example Components of a Project Management Plan
7
Questions

Related Posts

๐Ÿ“˜ Section 44: Control Scope
May 15, 2025
5 min
ยฉ 2025, All Rights Reserved.
Powered By

Quick Links

About Me

Legal Stuff

Social Media