Performing Integrated Change Control is the process of reviewing, analyzing, and approving or rejecting all change requests. It ensures changes are aligned with the projectโs objectives and do not disrupt its baselines unless absolutely necessary.
This process is part of the Monitoring and Controlling Process Group and integrates changes across the entire project lifecycle.
Receive the Change Request:
Log the change request in the change log for tracking.
Analyze the Change:
Evaluate the changeโs impact on scope, schedule, cost, quality, and risks.
Consult the Change Control Board (CCB):
Discuss the request with the CCB or stakeholders for approval/rejection.
Update Project Documents:
If approved, update relevant baselines, risk registers, and other documents.
Communicate the Decision:
Inform stakeholders of the decision and any resulting changes.
Scenario: A stakeholder submits a change request to add a new feature to the project. Implementing this change will increase the project cost by 10% and delay delivery by two weeks.
Question:
What should the project manager do first?
a. Implement the change to satisfy the stakeholder.
b. Evaluate the impact of the change on the project baselines.
c. Reject the change because it delays the project timeline.
d. Escalate the decision to the project sponsor.
Correct Answer: b. The impact must be evaluated before making a decision.
Scenario: A change request to adjust the project schedule has been approved.
Question:
What is the next step for the project manager?
a. Communicate the approval to the team and stakeholders.
b. Begin implementing the change immediately.
c. Update the risk register to reflect potential impacts of the change.
d. Revise the project management plan and baselines.
Correct Answer: d. Approved changes require updates to the project management plan and baselines before implementation.
Scenario: A team member implements a change without going through the change control process.
Question:
What should the project manager do?
a. Allow the change if it improves project outcomes.
b. Reverse the change and document the incident in the issue log.
c. Escalate the issue to the sponsor.
d. Update the change log to include the unauthorized change.
Correct Answer: b. Unauthorized changes should be reversed, and the incident must be documented.
Scenario: A change request impacts the projectโs cost and schedule. After approval, the project sponsor asks for a summary of the impact.
Question:
What document should the project manager provide?
a. Change Log
b. Updated Project Management Plan
c. Work Performance Reports
d. Lessons Learned Register
Correct Answer: b. The updated project management plan includes the revised baselines reflecting the change.
Scenario: The project is receiving multiple change requests from different stakeholders, which are starting to overwhelm the project team.
Question:
What should the project manager do?
a. Approve the most urgent changes and reject the rest.
b. Prioritize the changes based on project objectives and analyze their impacts.
c. Pause the project to process the change requests.
d. Escalate the issue to the change control board.
Correct Answer: b. Changes should be prioritized and analyzed for their impact before approval.
Quick Links
Legal Stuff
Social Media