HomeAbout Me

📘 Section 37: Closing the Project or Phase

By Daniel Nguyen
Published in PMP
April 13, 2025
3 min read
📘 Section 37: Closing the Project or Phase

Closing the Project or Phase is the final process in the Project Integration Management knowledge area. It involves finalizing all activities, obtaining formal acceptance, and ensuring all project objectives are met. This step confirms that the project or phase is complete, lessons learned are documented, and resources are released.


Key Aspects of Closing the Project or Phase

1. Inputs

  • Project Charter: Contains initial project objectives and success criteria.
  • Project Management Plan: Includes baselines and subsidiary plans.
  • Project Documents: Such as issue logs, risk registers, and assumption logs.
  • Accepted Deliverables: Approved deliverables verified in the validation process.
  • Organizational Process Assets (OPAs): Includes closure guidelines, templates, and historical information.

2. Tools and Techniques

  • Data Analysis:
    • Regression analysis, trend analysis, and variance analysis to evaluate performance.
  • Meetings:
    • Lessons learned, knowledge sharing, and final project reviews.
  • Expert Judgment:
    • Consulting experts to validate closure processes.

3. Outputs

  • Final Product, Service, or Result Transition: The deliverable is handed over to the customer or operations team.
  • Final Report: Summarizes project performance, achievement of objectives, and stakeholder satisfaction.
  • Updates to Organizational Process Assets (OPAs):
    • Includes lessons learned, project records, and closure documentation.

Steps in Closing the Project or Phase

  1. Review and Validate Deliverables
    Ensure all deliverables meet acceptance criteria and have been formally approved.

  2. Confirm Completion of Work
    Verify that all project work has been performed as outlined in the project plan.

  3. Transfer Ownership
    Hand over deliverables to the customer or operational team.

  4. Document Lessons Learned
    Capture experiences, successes, and challenges to improve future projects.

  5. Release Resources
    Reassign or release team members and materials.

  6. Archive Records
    Save all project documents, contracts, and reports for future reference.


Scenario-Based Questions

1. Ensuring Completion

Scenario: Your project team has delivered the final product to the customer. However, you notice that the lessons learned have not been documented yet.
Question:
What should the project manager do?
a. Proceed to close the project without documenting lessons learned.
b. Conduct a lessons learned meeting before project closure.
c. Inform the sponsor that the project is complete.
d. Archive project documents and move to the next project.
Correct Answer: b. Lessons learned are a critical part of the closure process.


2. Addressing Unresolved Issues

Scenario: During project closure, a stakeholder points out that a minor deliverable is missing. This issue was not documented earlier.
Question:
What should the project manager do?
a. Ignore the issue since it was not documented.
b. Address the issue and complete the deliverable before closure.
c. Inform the sponsor and seek their guidance.
d. Close the project and document the issue in lessons learned.
Correct Answer: b. All deliverables must be completed before project closure.


3. Transitioning Deliverables

Scenario: The project deliverable is complete, but the customer is hesitant to accept it due to a lack of operational readiness.
Question:
What should the project manager do?
a. Close the project and consider the deliverable accepted.
b. Work with the customer to ensure readiness and provide necessary training.
c. Escalate the issue to the project sponsor for a decision.
d. Update the risk register with the customer’s feedback.
Correct Answer: b. Ensuring customer readiness is crucial for successful project closure.


4. Handling Incomplete Work

Scenario: During the final review, it is discovered that some non-critical deliverables were not completed. The customer agrees to close the project without them.
Question:
What should the project manager do?
a. Document the incomplete work in the final report.
b. Reopen the project to complete the deliverables.
c. Close the project without further action.
d. Inform the project sponsor of the incomplete work.
Correct Answer: a. Documenting incomplete work ensures transparency and accountability.


5. Archiving Documents

Scenario: After project closure, a team member points out that some important project documents are missing from the archive.
Question:
What should the project manager do?
a. Ignore the missing documents since the project is closed.
b. Recreate the documents from memory and archive them.
c. Review document management practices and retrieve the missing files.
d. Inform the project sponsor about the missing documents.
Correct Answer: c. Reviewing document management practices ensures the completeness of the archive.


6. Final Report

Scenario: The project is completed, and the sponsor requests a summary of the project’s outcomes, lessons learned, and final costs.
Question:
What document should the project manager prepare?
a. Final Report
b. Project Charter
c. Risk Register
d. Project Management Plan
Correct Answer: a. The final report provides a summary of project outcomes.


Example Final Report Outline

  • Executive Summary: High-level overview of project objectives and outcomes.
  • Project Objectives and Achievements: Compare planned vs. actual results.
  • Stakeholder Satisfaction: Evaluate how well the project met stakeholder expectations.
  • Lessons Learned: Key insights and areas for improvement.
  • Financial Summary: Budget performance, including variances.
  • Transition Plan: Details of handover to operations or the customer.

Let me know if you’d like further details or more scenario-based questions!


Tags

#PMP

Share

Previous Article
📘 Section 36: Performing Integrated Change Control
Next Article
Quick Sort

Table Of Contents

1
Key Aspects of Closing the Project or Phase
2
Steps in Closing the Project or Phase
3
Scenario-Based Questions

Related Posts

📘 Section 44: Control Scope
May 15, 2025
5 min
© 2025, All Rights Reserved.
Powered By

Quick Links

About Me

Legal Stuff

Social Media