Closing the Project or Phase is the final process in the Project Integration Management knowledge area. It involves finalizing all activities, obtaining formal acceptance, and ensuring all project objectives are met. This step confirms that the project or phase is complete, lessons learned are documented, and resources are released.
Review and Validate Deliverables
Ensure all deliverables meet acceptance criteria and have been formally approved.
Confirm Completion of Work
Verify that all project work has been performed as outlined in the project plan.
Transfer Ownership
Hand over deliverables to the customer or operational team.
Document Lessons Learned
Capture experiences, successes, and challenges to improve future projects.
Release Resources
Reassign or release team members and materials.
Archive Records
Save all project documents, contracts, and reports for future reference.
Scenario: Your project team has delivered the final product to the customer. However, you notice that the lessons learned have not been documented yet.
Question:
What should the project manager do?
a. Proceed to close the project without documenting lessons learned.
b. Conduct a lessons learned meeting before project closure.
c. Inform the sponsor that the project is complete.
d. Archive project documents and move to the next project.
Correct Answer: b. Lessons learned are a critical part of the closure process.
Scenario: During project closure, a stakeholder points out that a minor deliverable is missing. This issue was not documented earlier.
Question:
What should the project manager do?
a. Ignore the issue since it was not documented.
b. Address the issue and complete the deliverable before closure.
c. Inform the sponsor and seek their guidance.
d. Close the project and document the issue in lessons learned.
Correct Answer: b. All deliverables must be completed before project closure.
Scenario: The project deliverable is complete, but the customer is hesitant to accept it due to a lack of operational readiness.
Question:
What should the project manager do?
a. Close the project and consider the deliverable accepted.
b. Work with the customer to ensure readiness and provide necessary training.
c. Escalate the issue to the project sponsor for a decision.
d. Update the risk register with the customer’s feedback.
Correct Answer: b. Ensuring customer readiness is crucial for successful project closure.
Scenario: During the final review, it is discovered that some non-critical deliverables were not completed. The customer agrees to close the project without them.
Question:
What should the project manager do?
a. Document the incomplete work in the final report.
b. Reopen the project to complete the deliverables.
c. Close the project without further action.
d. Inform the project sponsor of the incomplete work.
Correct Answer: a. Documenting incomplete work ensures transparency and accountability.
Scenario: After project closure, a team member points out that some important project documents are missing from the archive.
Question:
What should the project manager do?
a. Ignore the missing documents since the project is closed.
b. Recreate the documents from memory and archive them.
c. Review document management practices and retrieve the missing files.
d. Inform the project sponsor about the missing documents.
Correct Answer: c. Reviewing document management practices ensures the completeness of the archive.
Scenario: The project is completed, and the sponsor requests a summary of the project’s outcomes, lessons learned, and final costs.
Question:
What document should the project manager prepare?
a. Final Report
b. Project Charter
c. Risk Register
d. Project Management Plan
Correct Answer: a. The final report provides a summary of project outcomes.
Let me know if you’d like further details or more scenario-based questions!
Quick Links
Legal Stuff
Social Media