In the context of Project Management Professional (PMP), the creation of a Work Breakdown Structure (WBS) occurs as part of the Create WBS process within the Scope Management Knowledge Area. Below are the inputs, tools and techniques, and outputs of the Create WBS process as defined in the PMBOK® Guide:
Project Management Plan
Project Documents
Enterprise Environmental Factors (EEFs)
Organizational Process Assets (OPAs)
Decomposition
Expert Judgment
Meetings
Scope Baseline
Project Documents Updates
A. To define the project’s cost baseline
B. To create a schedule for project activities
C. To define the total scope of the project
D. To assign resources to project tasks
Answer: C. To define the total scope of the project
Explanation: The WBS is a hierarchical decomposition of the total scope of work, ensuring all deliverables are accounted for.
A. The project must be completed within the budget.
B. Each WBS element should account for 100% of the work required for the parent element.
C. Each task must take no longer than 100% of the estimated time.
D. Each deliverable must be assigned to 100% of the project team.
Answer: B. Each WBS element should account for 100% of the work required for the parent element.
Explanation: The 100% Rule ensures the WBS captures all project deliverables and scope.
A. Deliverable
B. Activity
C. Work Package
D. Milestone
Answer: C. Work Package
Explanation: A work package is the smallest unit of work in the WBS, which can be estimated, assigned, and managed.
A. The WBS focuses on the “what,” while the activity list focuses on the “how.”
B. The WBS includes cost information, while the activity list does not.
C. The WBS is created during execution, while the activity list is created during initiation.
D. The WBS focuses on time estimation, while the activity list focuses on scope.
Answer: A. The WBS focuses on the “what,” while the activity list focuses on the “how.”
Explanation: The WBS defines what deliverables need to be produced, while the activity list identifies how to achieve them.
A. Project Charter
B. Requirements Documentation
C. Scope Baseline
D. Schedule Baseline
Answer: C. Scope Baseline
Explanation: The scope baseline includes the WBS, WBS dictionary, and project scope statement.
A. Resource assignments
B. Budget estimates
C. Detailed descriptions of each WBS element
D. Project milestones
Answer: C. Detailed descriptions of each WBS element
Explanation: The WBS dictionary provides additional details about each WBS element, such as scope, deliverables, and acceptance criteria.
A. Better communication of project scope
B. Enhanced team collaboration
C. Improved time management
D. Simplified cost tracking
Answer: C. Improved time management
Explanation: While a WBS indirectly aids in time management, its primary purpose is to define and manage project scope.
A. Lack of a detailed activity list
B. Incomplete WBS
C. Poor stakeholder communication
D. Unclear quality requirements
Answer: B. Incomplete WBS
Explanation: An incomplete WBS can lead to scope gaps, resulting in frequent scope changes as issues are discovered later.
A. Initiating
B. Planning
C. Executing
D. Monitoring and Controlling
Answer: B. Planning
Explanation: The WBS is created during the Planning Process Group as part of the Scope Management processes.
A. All project risks are identified
B. The project scope is decomposed into manageable parts
C. Resources are assigned to all deliverables
D. The project schedule is accurately estimated
Answer: B. The project scope is decomposed into manageable parts
Explanation: A well-defined WBS ensures the project scope is organized and manageable.
Would you like more scenario-based WBS questions or explanations? 😊
Quick Links
Legal Stuff
Social Media