Validate Scope is a process in the Monitoring and Controlling process group and part of the Scope Management knowledge area in project management. The purpose is to formally accept completed deliverables by ensuring they meet stakeholder requirements.
Focus on Deliverables
Stakeholder Involvement
Performed Periodically
Different from Quality Control
Project Management Plan
Project Documents
Verified Deliverables
Work Performance Data
Inspection
Decision-Making
Accepted Deliverables
Work Performance Information
Change Requests
Project Documents Updates
You are managing a software development project. During a client review session, the stakeholders reject the user authentication module, citing missing functionality that was part of the documented requirements.
What should you do first as the project manager?
A. Escalate the issue to the project sponsor for resolution.
B. Review the requirements documentation and acceptance criteria.
C. Reassign the module to the development team for rework.
D. Create a new change request to include the missing functionality.
Correct Answer:
B. Review the requirements documentation and acceptance criteria.
Explanation:
Before taking any action, you must verify whether the rejected functionality is indeed part of the documented requirements and acceptance criteria. This ensures clarity and avoids unnecessary rework.
Your project team completes a major deliverable ahead of schedule. You are preparing for a stakeholder review to validate the deliverable. However, one key stakeholder is unavailable to attend the review meeting.
What should you do?
A. Proceed with the review and document the stakeholder’s absence.
B. Reschedule the review to ensure all stakeholders are present.
C. Obtain input from the stakeholder after the review.
D. Delay the review until the stakeholder is available.
Correct Answer:
B. Reschedule the review to ensure all stakeholders are present.
Explanation:
Validation of deliverables requires input and approval from all key stakeholders. Rescheduling ensures their feedback is incorporated and formal acceptance can be obtained.
While validating a deliverable, you discover that it meets the acceptance criteria but deviates from the initial project scope. This deviation was caused by an unapproved scope change introduced during execution.
What is the best course of action?
A. Accept the deliverable since it meets the acceptance criteria.
B. Reject the deliverable and raise a corrective action request.
C. Escalate the issue to the project sponsor for guidance.
D. Review the change control process to address the unapproved change.
Correct Answer:
D. Review the change control process to address the unapproved change.
Explanation:
Unapproved scope changes must be addressed through the change control process to ensure proper documentation and accountability. Even if the deliverable meets acceptance criteria, such changes must follow established procedures.
During a Validate Scope session, the client requests additional features to enhance a deliverable. These features were not included in the initial scope.
What should you do?
A. Reject the request, as it is outside the initial scope.
B. Approve the request to maintain a good relationship with the client.
C. Raise a change request and evaluate the impact of the additional features.
D. Implement the changes only if the team can complete them within the current schedule.
Correct Answer:
C. Raise a change request and evaluate the impact of the additional features.
Explanation:
The change control process must be followed to evaluate the impact of the requested features on scope, schedule, and cost. Only approved changes should be implemented.
You complete the Validate Scope process for a deliverable, and most stakeholders approve it. However, one key stakeholder is dissatisfied and refuses to sign off.
What should you do next?
A. Proceed with the project, as the majority of stakeholders have approved the deliverable.
B. Escalate the issue to the project sponsor.
C. Work with the dissatisfied stakeholder to understand their concerns.
D. Document the disagreement and move forward with the project.
Correct Answer:
C. Work with the dissatisfied stakeholder to understand their concerns.
Explanation:
It is essential to address the concerns of all key stakeholders to achieve formal acceptance. Collaborating with the dissatisfied stakeholder ensures their feedback is considered and avoids potential conflicts later.
Quick Links
Legal Stuff
Social Media