Control Scope is a process in the Monitoring and Controlling Process Group and part of the Scope Management Knowledge Area. The purpose of this process is to monitor the project scope and manage changes to the scope baseline, ensuring the project remains on track and within approved boundaries.
Focus on Baseline
Variance Monitoring
Change Management
Stakeholder Communication
Project Management Plan
Project Documents
Work Performance Data
Organizational Process Assets (OPAs)
Variance Analysis
Trend Analysis
Change Control Tools
Data Analysis
Work Performance Information
Change Requests
Project Management Plan Updates
Project Documents Updates
A construction project is delayed because of unexpected weather conditions. A stakeholder requests adding an additional feature to the building. The project manager:
During project execution, the marketing team requests several changes to the deliverables, stating that these changes are necessary due to market trends. These requests are starting to cause delays in the project schedule.
What should you do as the project manager?
A. Deny all future change requests to avoid further delays.
B. Implement changes that have minimal impact on the schedule.
C. Evaluate each change request through the integrated change control process.
D. Instruct the team to continue work based on the original scope baseline.
Correct Answer:
C. Evaluate each change request through the integrated change control process.
Explanation:
The Control Scope process ensures that all changes are reviewed and evaluated for their impact on scope, schedule, cost, and quality before being approved or rejected.
A stakeholder has requested additional functionality during a project meeting. They insist that this change must be implemented immediately and do not want to go through the formal change request process.
How should you respond?
A. Implement the requested change to satisfy the stakeholder.
B. Politely inform the stakeholder that changes must follow the change control process.
C. Escalate the issue to the project sponsor.
D. Reject the change outright to maintain the project schedule.
Correct Answer:
B. Politely inform the stakeholder that changes must follow the change control process.
Explanation:
All changes must be evaluated and approved through the change control process to avoid scope creep and maintain project integrity.
You are reviewing the progress of a project deliverable and notice that the team has been working on additional features that were not part of the original scope. These features were added based on assumptions made by the development team.
What should you do next?
A. Approve the additional features as they may add value to the deliverable.
B. Immediately stop work on the additional features and remove them.
C. Evaluate the impact of the additional features and process them through change control.
D. Allow the team to continue as the changes do not significantly affect the schedule.
Correct Answer:
C. Evaluate the impact of the additional features and process them through change control.
Explanation:
Changes made without approval must be reviewed for their impact and processed through the change control system. This ensures that only authorized changes are implemented.
Your project is behind schedule, and a senior manager questions whether scope changes have contributed to the delays. You realize that no formal record of scope changes has been maintained.
What should you do to address this issue?
A. Conduct a retrospective meeting to identify undocumented scope changes.
B. Update the project management plan to reflect the current status.
C. Use the requirements traceability matrix to identify scope changes.
D. Implement stricter change control policies going forward.
Correct Answer:
C. Use the requirements traceability matrix to identify scope changes.
Explanation:
The requirements traceability matrix helps link scope changes to requirements and deliverables, making it easier to track unauthorized changes.
While analyzing scope performance, you find that the project is deviating from the scope baseline due to unclear requirements provided during the planning phase.
What should you do to address the variance?
A. Raise a change request to revise the scope baseline.
B. Conduct a root cause analysis to address the unclear requirements.
C. Reject all deliverables that deviate from the baseline.
D. Reassess the project charter for scope clarification.
Correct Answer:
B. Conduct a root cause analysis to address the unclear requirements.
Explanation:
Identifying the root cause of the variance ensures that you can take corrective or preventive actions to prevent future scope issues.
During a scope review, a stakeholder identifies missing functionality that was not included in the original scope. The stakeholder insists this functionality is critical for the projectβs success.
What should you do next?
A. Add the functionality to the deliverables to satisfy the stakeholder.
B. Escalate the issue to the project sponsor for resolution.
C. Process the request through the integrated change control process.
D. Inform the stakeholder that no changes can be made at this stage.
Correct Answer:
C. Process the request through the integrated change control process.
Explanation:
Any new requirements or changes must go through the change control process to assess their impact on the project.
Quick Links
Legal Stuff
Social Media