HomeAbout Me

πŸ“˜ Section 44: Control Scope

By Daniel Nguyen
Published in PMP
May 15, 2025
5 min read
πŸ“˜ Section 44: Control Scope

Control Scope is a process in the Monitoring and Controlling Process Group and part of the Scope Management Knowledge Area. The purpose of this process is to monitor the project scope and manage changes to the scope baseline, ensuring the project remains on track and within approved boundaries.


Purpose of Control Scope

  1. Prevent scope creep (uncontrolled scope changes).
  2. Ensure that changes to scope are processed through the Perform Integrated Change Control process.
  3. Maintain alignment between project work and stakeholder expectations.
  4. Monitor the status of the project scope to identify variances.

Key Features of Control Scope

  1. Focus on Baseline

    • Ensures work is performed according to the scope baseline (defined in the Project Management Plan).
  2. Variance Monitoring

    • Compares actual performance to planned scope and identifies deviations.
  3. Change Management

    • Incorporates only approved changes and updates to the scope baseline.
  4. Stakeholder Communication

    • Keeps stakeholders informed about scope changes and their impacts.

Inputs for Control Scope

  1. Project Management Plan

    • Scope Management Plan: Defines how scope changes will be controlled.
    • Scope Baseline: Serves as a reference for tracking deviations.
    • Performance Measurement Baseline: Helps measure project performance.
  2. Project Documents

    • Lessons Learned Register: Guides scope control based on past experiences.
    • Requirements Documentation: Tracks requirements to ensure all are met.
    • Requirements Traceability Matrix: Links requirements to deliverables.
  3. Work Performance Data

    • Provides data on work completed and its alignment with the scope baseline.
  4. Organizational Process Assets (OPAs)

    • Includes policies, procedures, and historical information for scope control.

Tools and Techniques for Control Scope

  1. Variance Analysis

    • Compares actual performance to the scope baseline to identify variances.
  2. Trend Analysis

    • Evaluates project performance trends to predict future scope deviations.
  3. Change Control Tools

    • Tools used to process scope change requests through the integrated change control process.
  4. Data Analysis

    • Techniques like root cause analysis to address scope issues.

Outputs of Control Scope

  1. Work Performance Information

    • Interpreted data showing scope performance and variances.
  2. Change Requests

    • Requests for corrective or preventive actions to address scope deviations. These are processed through the Perform Integrated Change Control process.
  3. Project Management Plan Updates

    • Updates to the scope baseline and other parts of the project management plan if changes are approved.
  4. Project Documents Updates

    • Updates to the requirements documentation and traceability matrix.

Best Practices for Controlling Scope

  1. Define a Clear Scope Baseline: Ensure the scope is well-defined and agreed upon during the planning phase.
  2. Use the Requirements Traceability Matrix: Helps track scope changes and their alignment with project goals.
  3. Engage Stakeholders Early: Ensure they are involved in identifying and approving scope changes.
  4. Enforce Change Control Processes: Only implement changes that are approved through the formal change control process.
  5. Communicate Scope Variances: Keep stakeholders informed about any deviations and their impacts.

Example Scenario

A construction project is delayed because of unexpected weather conditions. A stakeholder requests adding an additional feature to the building. The project manager:

  1. Evaluates the request against the scope baseline.
  2. Processes the request through the Perform Integrated Change Control process.
  3. Updates the scope baseline if the change is approved and revises project documents accordingly.

Scenario-Based PMP Questions: Control Scope


Scenario 1: Frequent Scope Changes

During project execution, the marketing team requests several changes to the deliverables, stating that these changes are necessary due to market trends. These requests are starting to cause delays in the project schedule.

Question:

What should you do as the project manager?

A. Deny all future change requests to avoid further delays.
B. Implement changes that have minimal impact on the schedule.
C. Evaluate each change request through the integrated change control process.
D. Instruct the team to continue work based on the original scope baseline.


Correct Answer:
C. Evaluate each change request through the integrated change control process.

Explanation:
The Control Scope process ensures that all changes are reviewed and evaluated for their impact on scope, schedule, cost, and quality before being approved or rejected.


Scenario 2: Stakeholder Demands Unapproved Changes

A stakeholder has requested additional functionality during a project meeting. They insist that this change must be implemented immediately and do not want to go through the formal change request process.

Question:

How should you respond?

A. Implement the requested change to satisfy the stakeholder.
B. Politely inform the stakeholder that changes must follow the change control process.
C. Escalate the issue to the project sponsor.
D. Reject the change outright to maintain the project schedule.


Correct Answer:
B. Politely inform the stakeholder that changes must follow the change control process.

Explanation:
All changes must be evaluated and approved through the change control process to avoid scope creep and maintain project integrity.


Scenario 3: Unidentified Scope Issue

You are reviewing the progress of a project deliverable and notice that the team has been working on additional features that were not part of the original scope. These features were added based on assumptions made by the development team.

Question:

What should you do next?

A. Approve the additional features as they may add value to the deliverable.
B. Immediately stop work on the additional features and remove them.
C. Evaluate the impact of the additional features and process them through change control.
D. Allow the team to continue as the changes do not significantly affect the schedule.


Correct Answer:
C. Evaluate the impact of the additional features and process them through change control.

Explanation:
Changes made without approval must be reviewed for their impact and processed through the change control system. This ensures that only authorized changes are implemented.


Scenario 4: Monitoring Scope Performance

Your project is behind schedule, and a senior manager questions whether scope changes have contributed to the delays. You realize that no formal record of scope changes has been maintained.

Question:

What should you do to address this issue?

A. Conduct a retrospective meeting to identify undocumented scope changes.
B. Update the project management plan to reflect the current status.
C. Use the requirements traceability matrix to identify scope changes.
D. Implement stricter change control policies going forward.


Correct Answer:
C. Use the requirements traceability matrix to identify scope changes.

Explanation:
The requirements traceability matrix helps link scope changes to requirements and deliverables, making it easier to track unauthorized changes.


Scenario 5: Scope Variance Detected

While analyzing scope performance, you find that the project is deviating from the scope baseline due to unclear requirements provided during the planning phase.

Question:

What should you do to address the variance?

A. Raise a change request to revise the scope baseline.
B. Conduct a root cause analysis to address the unclear requirements.
C. Reject all deliverables that deviate from the baseline.
D. Reassess the project charter for scope clarification.


Correct Answer:
B. Conduct a root cause analysis to address the unclear requirements.

Explanation:
Identifying the root cause of the variance ensures that you can take corrective or preventive actions to prevent future scope issues.


Scenario 6: Unexpected Stakeholder Feedback

During a scope review, a stakeholder identifies missing functionality that was not included in the original scope. The stakeholder insists this functionality is critical for the project’s success.

Question:

What should you do next?

A. Add the functionality to the deliverables to satisfy the stakeholder.
B. Escalate the issue to the project sponsor for resolution.
C. Process the request through the integrated change control process.
D. Inform the stakeholder that no changes can be made at this stage.


Correct Answer:
C. Process the request through the integrated change control process.

Explanation:
Any new requirements or changes must go through the change control process to assess their impact on the project.



Tags

#PMP

Share

Previous Article
React Hooks 4: DOM Side-Effects

Table Of Contents

1
Purpose of Control Scope
2
Key Features of Control Scope
3
Inputs for Control Scope
4
Tools and Techniques for Control Scope
5
Outputs of Control Scope
6
Best Practices for Controlling Scope
7
Example Scenario
8
Scenario-Based PMP Questions: Control Scope

Related Posts

πŸ“˜ Section 42: Create Work Breakdown Structure
May 10, 2025
3 min
Β© 2025, All Rights Reserved.
Powered By

Quick Links

About Me

Legal Stuff

Social Media